Uber Eats integrated campaign operations

Campaign operations and delivery tracking for integrated Uber Eats work, run across Japan and Australia teams.

Client
Uber Eats
Year
2025–
Category
Integrated Campaign Operations
Role
Project Manager / Creative Operations
Cross-functional stakeholders
20+Cross-functional stakeholders
Cross-office delivery
Japan + AustraliaCross-office delivery
Project duration
5–7 moProject duration
Campaign budget
USD 2M+Campaign budget
Concurrent workstreams
MultipleConcurrent workstreams
Bilingual delivery environment
EN / JABilingual delivery environment

Project-scope indicators, not personal achievement claims.

Overview

Integrated Uber Eats campaign work delivered under the same cross-office operating model as the Uber Taxi programme. My role covered schedule ownership, resource coordination, production tracking and stakeholder communication across the delivery cycle.

Context

Uber Eats work ran alongside other live campaigns rather than in isolation, sharing creative and production resource with concurrent projects. Coordination therefore had to account for what else was in flight, not only what this campaign needed.

Challenge

Concurrent campaigns drawing on the same people meant a change in one project moved capacity in another. Keeping delivery predictable required tracking dependencies across projects, not just within this one.

Scope

Scope

  • Campaign schedule across creative, production and localization
  • Resource coordination against other concurrent campaign work
  • Cross-office alignment between Japan and Australia teams
  • Production tracking and delivery readiness
  • Status reporting and stakeholder communication
  • Budget visibility against plan
  • Change request handling and downstream impact assessment

Team

Team

  • 20+ people across Japan and Australia

Stakeholders

Creative, integrated production, account management, media, finance, external partners and client-side stakeholders.

Role and ownership

What the organization delivered

The agency delivered integrated Uber Eats campaign work for the Japanese market across creative, production and localization.

What I personally owned

  • Owned the campaign schedule and its dependencies on concurrent work
  • Coordinated shared creative and production resource across live projects
  • Tracked production status and delivery readiness through to handoff
  • Assessed and communicated the downstream impact of change requests
  • Maintained budget visibility and flagged variance against plan
  • Ran bilingual status communication across Japan and Australia stakeholders

What resulted

  • Helped teams execute integrated Uber Taxi and Uber Eats campaigns over 5–7 month delivery cycles
  • Supported campaign operations across budgets exceeding USD 2 million
  • Made creative timelines more manageable by clarifying ownership, dependencies, approvals and escalation points
  • Maintained visibility, ownership and delivery control across multiple concurrent workstreams

Operating model

Cross-project resource view

Capacity was read across all live campaigns at once, so a change here was visible as a change everywhere.

Change with stated impact

Change requests carried an explicit downstream cost in dates and resource before they were accepted.

Readiness over status

Reporting tracked whether a deliverable was ready to move, not only what percentage was done.

Shared escalation path

One escalation route across both offices rather than separate local chains.

An overhead view of a long printed schedule laid across a desk between two closed notebooks, one bar marked in blue.
Representative working environment. One schedule, shared across both offices.

Tools and systems

  • Asana
  • Google Workspace
  • Slack
  • Spreadsheet-based resource and budget tracking
  • Shared review and approval workflows

Risks and constraints

Risks and constraints

  • Shared resource contention with concurrent campaigns
  • Change requests arriving after production dates were locked
  • Cross-office approval latency
  • Localization dependencies affecting delivery dates
  • Partner and vendor availability during peak periods

Key decisions

  1. 01

    Price every change in dates

    No change request moved forward without its schedule and resource impact stated, so trade-offs were made deliberately rather than absorbed.

  2. 02

    Read capacity across projects

    Resource was planned at portfolio level rather than per campaign, because the same people served several campaigns at once.

  3. 03

    Report readiness, not percentage

    Status reporting answered whether the next step could start, which is the question leadership actually needed answered.

Deliverables

Deliverables

  • Campaign delivery schedule
  • Cross-project resource view
  • Change request log with impact assessment
  • Production tracker
  • Weekly status reporting
  • Budget status view against plan

What changed

Concurrent campaigns stopped being planned as if each had the team to itself. Resource conflicts surfaced while they were still solvable rather than at the point of delivery.

Lessons learned

  1. In a shared-resource environment, a project plan that ignores neighbouring projects is fiction.
  2. Change is manageable when its cost is stated; it becomes damage when it is absorbed silently.
  3. Leadership needs readiness, not completion percentage.